FRIDAY, MAY 20, 2011
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The contractor continued installing the metal track for the wood panel system on the 2nd Floor.
- Workers continued installing the med gas system on the 2nd Floor.
- The contractor continued erecting the 2nd floor elevator lobby doorframe on the MEB side of the lobby.
- Crews continued installing the restroom partitions in the Women’s restroom on the 1st Floor.
RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:
- The contractor installed wiring for fuel storage system.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor continued installing the generator fuel line on the 8th Floor
CEB PERMANENT REPAIRS & MITIGATION:
- The contractor continued installing electrical conduits on the 1st and 3rd Floors.
- Crews are removing the elevator shaft in the library area.
CEB COVERED WALKWAY:
- The contractor continued installing metal roof panels and flashing on canopy B at the end closest to the Clinical Education Building.
CSRB EXHAUST UPGRADE:
- The contractor installed the plenum support for Exhaust System 4.
- The demolition of the ceiling on the 2nd Floor has been completed.
DENTAL SCHOOL AHU REPLACEMENT PROJECT:
- The contractor continued insulating the supply duct for units 8A & 8D in the Clinic Building.
- Crews continued installing the VAV boxes on the 3rd Floor of the Administration Building.
DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:
- The contractor continued installing new caulk on the north and east sides of the Clinic Building and the west side of the Administration Building.