Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, MAY 20, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing the metal track for the wood panel system on the 2nd Floor.  
  • Workers continued installing the med gas system on the 2nd Floor.
  • The contractor continued erecting the 2nd floor elevator lobby doorframe on the MEB side of the lobby.
  • Crews continued installing the restroom partitions in the Women’s restroom on the 1st Floor.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor installed wiring for fuel storage system.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing the generator fuel line on the 8th Floor

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduits on the 1st and 3rd Floors.
  • Crews are removing the elevator shaft in the library area.

CEB COVERED WALKWAY:

  • The contractor continued installing metal roof panels and flashing on canopy B at the end closest to the Clinical Education Building.

CSRB EXHAUST UPGRADE:

  • The contractor installed the plenum support for Exhaust System 4.
  • The demolition of the ceiling on the 2nd Floor has been completed.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued insulating the supply duct for units 8A & 8D in the Clinic Building.
  • Crews continued installing the VAV boxes on the 3rd Floor of the Administration Building. 

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued installing new caulk on the north and east sides of the Clinic Building and the west side of the Administration Building.