Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, MAY 23, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing the metal track for the wood panel system on the 2nd floor.  
  • Workers continued installing the med gas system on the 2nd Floor.
  • They continued installing the restroom partitions in the Womens restroom on the 1st Floor.
  • Ceiling grid is being installed on the 2nd Floor along the MEB loading dock side of the building.
  • The contractor started installing conduit for the light fixtures in the Tiger Room. 

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor touched up paint for doors on the 2nd level of the new building.
  • They insulated the domestic water pipe on the C-tower side of the 1st Floor.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing the generator fuel line on the 8th Floor.
  • Crews began installing the piping manifold for the domestic hot water pumps in the 2nd Floor pump room.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding and installing chilled water pipe in the basement.
  • They continued installing electrical conduits on the 1st Floor.
  • Workers continued removing the elevator shaft in the library area.
  • The contractor drove 7 wooden piles in the Lakeside lot. 31 of a total of 110 piles are now in place.

CSRB EXHAUST UPGRADE:

  • The contractor installed the exhaust duct riser for Exhaust System #4 on the 3rd Floor.

CEB COVERED WALKWAY:

  • The contractor continued installing flashing on canopy B at the end closest to the Clinical Education Building.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued insulating the supply duct and heating hot water lines for units 8A & 8D in the Clinic Building.
  • Crews ran control wires for 8A and 8D.
  • The fire alarm devices for unit 8D were installed. 
  • The contractor started running unit 8A. 
  • The contractor continued installing the VAV boxes and began running reheat lines on the 3rd Floor of the Administration Building.

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued to remove the existing caulk from the joints between the exterior wall panels.
  • Crews continued installing new backer rod and caulk on the north and east sides of the Clinic Building and the west side of the Administration Building.