ALLIED HEALTH/NURSING BUILDING PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing the metal track for the wood panel system on the 2nd Floor.  
  • They continued installing the med gas system on the 2nd Floor.
  • Workers finished installing the restroom partitions in the Womens restroom on the 1st Floor.

RESIDENCE HALL PERMANENT REPAIRS & MITIGATION:

  • The contractor insulated the generator exhaust pipe on the 2nd level of the new building.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing the generator fuel line on the 8th Floor.
  • They began installing the controls on the 1st Floor air handling units (AHUs).

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding and installing chilled water pipe in the basement.
  • They continued installing electrical conduits on the 1st Floor.
  • Crews continued removing the elevator shaft in the library area.
  • The contractor drove 10 piles (41 of 110) in the Lakeside lot.

CSRB EXHAUST UPGRADE:

  • The contractor continued to layout equipment on the roof.

CEB COVERED WALKWAY:

  • The contractor finished installing the flashing on canopy B at the end of the walkway closest to the Clinical Education Building.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued insulating the supply duct and heating hot water lines for units 8A & 8D in the Clinic Building.
  • Crews ran control wires for AHU 8A and 8D.
  • The contractor put unit 8C into operation. 
  • The contractor continued running reheat water lines on the 3rd Floor of the Administration Building. 

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued installing new caulk on the north and east sides of the Clinic Building and the west side of the Administration Building.