MONDAY, MAY 30, 2011
NOTE: Many of the contractors observed the Memorial Day Holiday.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor continued installing the electrical conduit for the fire pump controller.
- Workers continued installing the generator fuel line in the office area on the 1st Floor.
CSRB EXHAUST UPGRADE:
- The contractor began installing temporary ductwork on the 2nd Floor.
- Crews cut the roof penetration for exhaust system #1.
DENTAL SCHOOL AHU REPLACEMENT PROJECT:
- The contractor installed the ceiling on the 8th Floor and continued removing the ceiling on the 3rd Floor.