FRIDAY, JUNE 10, 2011
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The contractor continued installing metal framing for the wood wall panels on the 2nd Floor.
- They continued installing the stud wall between the mechanical room and auditorium on the 2nd Floor.
- Electrical conduits were installed in the 2nd Floor auditorium.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor continued welding the containment pipe for the diesel fuel line on the 8th Floor.
CEB PERMANENT REPAIRS & MITIGATION:
- The contractor continued installing electrical conduits on the 3rd Floor.
- Crews continued demolishing the elevator shaft wall in the basement.
- The contractor poured concrete for the areaway around the exterior of the Lakeside lot.
- Workers began to install gypsum board along the window wall in 3rd Floor offices.
DENTAL SCHOOL AHU REPLACEMENT PROJECT:
- The contractor installed control wires for VAV boxes on the 3rd Floor of the Clinic Building.
- They installed chill water pipes for unit 3B on the 3rd Floor.