TUESDAY, JUNE 14, 2011
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:
- The contractor continued installing metal framing for the wall panels on the 2nd Floor.\
- Crews continued to pre-fabricate the heating hot water lines for the bridge area.
- The contractor set toilet fixtures in the 1st Floor restrooms.
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor insulated water piping on the 1st Floor.
- Workers installed wiring for the fire pump on the 2nd Floor.
- Concrete was poured in the ATS room on the 2nd Floor.
CEB PERMANENT REPAIRS & MITIGATION:
- The contractor continued installing electrical conduit on the 3rd Floor.
- They continued demolishing the elevator shaft wall in the basement.
- The contractor continued removing the concrete forms for the areaway around the exterior of the Lakeside lot.
DENTAL SCHOOL AHU REPLACEMENT PROJECT:
- The contractor continued installing heating hot water lines for unit 3-B in the Clinic Building.
- Supply ductwork for unit 3-B was installed.
- The contractor continued installing ceiling grid on the 2nd Floor of the Administration Building.
- Crews installed the final VAV for L2A.
DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:
- Work continues on the west and east sides of the Clinic Building and on the north side of the Administration Building.