Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, JUNE 14, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing metal framing for the wall panels on the 2nd Floor.\
  • Crews continued to pre-fabricate the heating hot water lines for the bridge area.       
  • The contractor set toilet fixtures in the 1st Floor restrooms. 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor insulated water piping on the 1st Floor.
  • Workers installed wiring for the fire pump on the 2nd Floor.
  • Concrete was poured in the ATS room on the 2nd Floor.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduit on the 3rd Floor.
  • They continued demolishing the elevator shaft wall in the basement.
  • The contractor continued removing the concrete forms for the areaway around the exterior of the Lakeside lot.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing heating hot water lines for unit 3-B in the Clinic Building.
  • Supply ductwork for unit 3-B was installed.   
  • The contractor continued installing ceiling grid on the 2nd Floor of the Administration Building.
  • Crews installed the final VAV for L2A. 

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:

  • Work continues on the west and east sides of the Clinic Building and on the north side of the Administration Building.