Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, JUNE 17, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing restroom fixtures on the 1st Floor. 
  • Crews continued pre-fabricating the heating hot water lines for the bridge area.       
  • The contractor installed light fixtures in the 2nd Floor corridors. 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding the fuel line on the 1st Floor.
  • They pulled fire alarm wires for the control panel on the 1st Floor.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduit on the 2nd Floor.
  • Workers are forming the elevator shaft wall in the basement.
  • The contractor began excavating for the pile caps.
  • The window walls along the 3rd Floor corridor offices were painted.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor has successfully completed all pressure testing on the re-heat lines. 
  • Workers continued installing chilled water and heating hot water lines to unit 3-B. 
  • The contractor continued installing supply ductwork for 3-B and started installing VAVs for unit 3-A.  

DS ASBESTOS ABATEMENT

  • The contractor completed the abatement in the mechanical room for unit 6-A.