Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, JUNE 27, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: 

  • The contractor continued installing the metal framing for the auditorium wall panel system.  
  • Crews continued to run AV conduit for the auditorium. 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor began installing wiring for the four heating water pumps on the mezzanine deck of the 2nd Floor pump room.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding the 8 inch chilled water line in the basement.
  • Workers continued installing conduits on 2nd Floor.
  • The contractor continued building forms for 3 of the 12 pile caps in the Lakeside lot.

CSRB EXHAUST UPGRADE:

  • The contractor relocated the construction wall to encompass additional ductwork on the 2nd Floor.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing heating hot water lines and supply ductwork for air handling unit 3A in the Clinic Building. 
  • The asbestos contractor completed the abatement related to AHU 6A. 
  • The contractor installed isolation valves on all units on the B-riser in the Clinic Building. 
  • Crews continued floating the sheetrock ceiling in the restroom and near Faculty Practice on the 2nd Floor of the Administration Building.   
  • The contractor started pre-fabricating the chilled water lines for the 4th Floor units. 

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor caulked on the west side of the Clinic Building and pressure washed the concrete fins on the north side of Clinic Building.