Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, JUNE 29, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: 

  • The contractor continued installing the metal framing for the auditorium wall panel system and ran additional AV conduit. 
  • Crews started installing metal panels underneath the walkway.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing wiring for the four heating hot water pumps on the mezzanine deck of the 2nd Floor pump room.
  • They continued welding the fuel line casing in the electrical rooms.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding the 8 inch chilled water line in the basement and installing conduits on the 2nd and 3rd Floors.
  • Workers installed steel rebar in the concrete forms for the first 3 pile caps and started form up the 4th pile cap for the new elevated mechanical/electrical enclosure in the Lakeside lot.

CSRB EXHAUST UPGRADE:

  • The insulation was removed from the old exhaust ductwork on the 2nd Floor.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing heating hot water lines and supply ductwork for unit 3A in the Clinic Building. 
  • The ductwork for units 3A and 3B was pressure tested. 
  • The contractor set the new AHU 3A.
  • The concrete pad for unit 6A in the Clinic Building was set in place.   
  • The contractor painted the sheetrock ceiling in the 2nd Floor restroom and near Faculty Practice in the Administration Building.   

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued caulking on the west side of the Clinic Building and on the penthouse of the Administration Building.