Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, JUNE 30, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: 

  • The contractor continued installing the metal framing for the auditorium wall panel system.  
  • The walkway floor drains were re-routed. 
  • The contractor started installing metal panels underneath the walkway.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding the diesel fuel line casing in the electrical rooms.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding the 8 inch chilled water line in the basement and installing conduits on the 2nd and 3rd Floors.
  • Crews continued to form up 2 more pile caps (5 of 12 total) in the Lakeside lot.
  • Workers continued forming up the freight elevator shaft wall in the basement.

CSRB EXHAUST UPGRADE:

  • The contractor continued to remove the insulation from the exhaust ductwork on the 2nd Floor.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing heating hot water lines and supply ductwork for unit 3A. 
  • They continued to insulate the ductwork for unit 3B. 
  • Crews demolished the existing doorway in the mechanical room for unit 6A.

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued caulking on the west side of the Clinic Building and on the penthouse of the Administration Building.