TUESDAY, JULY 12, 2011
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: 
- The contractor installed sheetrock for the rear wall of the auditorium.
- They welded in additional structural supports for the new monumental staircase. 
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor continued welding the fuel line casing on the 1st and 8th Floors.
CEB PERMANENT REPAIRS & MITIGATION:
- The contractor continued installing conduits on the 2nd Floor.
- Crews erected the 9th pile cap concrete form in the Lakeside lot.
- They continued forming the freight elevator shaft wall in the basement.
CSRB EXHAUST UPGRADE PROJECT:
- The contractor began installing new ductwork on the 2nd Floor.
- They continued installing pitch pockets (roof penetrations for utilities) on the roof for exhaust systems 1 – 4.
- The contractor began relocating fire alarms and electrical devices on the 2nd Floor.
DENTAL SCHOOL AHU REPLACEMENT PROJECT:
- The contractor continued installing heating hot water lines for unit 6A in the Clinic Building. 
- Workers are installing supply ductwork for unit 3B. 
- Crews continued insulating ductwork and heating hot water lines for unit 3A. 
- They began putting up the ceiling grid up for unit 3A. 
DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:
- The contractor continued pressure washing the north and east side of the Power Plant.