WEDNESDAY, JULY 13, 2011
ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: 
- The contractor installed additional sheetrock for the rear wall of the auditorium.
- Workers grouted the structural supports for the new monumental staircase. 
RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:
- The contractor continued welding the fuel line casing on the 1st Floor.
CEB PERMANENT REPAIRS & MITIGATION:
- The contractor continued installing conduits on the 2nd Floor.
- Rebar has been installed in 9 of 12 concrete forms for the pile caps in the Lakeside lot.
- Crews continued forming the freight elevator shaft wall in the basement.
CSRB EXHAUST UPGRADE PROJECT:
- The contractor continued installing new ductwork on the 2nd Floor.
- They are installing roof flashing for exhaust systems 1 and 2.
- The 2nd Floor fire alarms and electrical devices have been relocated.
DENTAL SCHOOL AHU REPLACEMENT PROJECT:
- The contractor continued installing heating hot water lines for unit 6A and supply ductwork for unit 3B in the Clinic Building.
- Workers continued insulating ductwork and heating hot water lines for unit 3A. 
- The contractor continued installing ceiling grid for unit 3A. 
- Light fixtures were removed from Room 3312N. 
- The contractor continued installing the controls for units L2A and L3A in the Administration Building. 
DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:
- The contractor continued pressure washing the north and east side of the Power Plant.