ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: 

  • The contractor installed additional sheetrock for the rear wall of the auditorium.
  • Workers grouted the structural supports for the new monumental staircase. 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding the fuel line casing on the 1st Floor.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduits on the 2nd Floor.
  • Rebar has been installed in 9 of 12 concrete forms for the pile caps in the Lakeside lot.
  • Crews continued forming the freight elevator shaft wall in the basement.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing new ductwork on the 2nd Floor.
  • They are installing roof flashing for exhaust systems 1 and 2.
  • The 2nd Floor fire alarms and electrical devices have been relocated.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing heating hot water lines for unit 6A and supply ductwork for unit 3B in the Clinic Building.
  • Workers continued insulating ductwork and heating hot water lines for unit 3A. 
  • The contractor continued installing ceiling grid for unit 3A. 
  • Light fixtures were removed from Room 3312N. 
  • The contractor continued installing the controls for units L2A and L3A in the Administration Building. 

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued pressure washing the north and east side of the Power Plant.