Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, JULY 14, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: 

  • The contractor continued installing sheetrock for the rear wall of the auditorium.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding the fuel line casing on the 1st Floor.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduits on the 2nd Floor.
  • Workers continued setting forms and installing steel rebar for 9 of 12 forms for the pile caps in the Lakeside lot.
  • The contractor continued forming the freight elevator shaft wall in the basement.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing ductwork on the 2nd Floor.
  • They continued installing roof flashing for exhaust systems 1 and 2.
  • The ceiling in Room 729 was removed.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing heating hot water lines for unit 6A in the Clinic Building. 
  • Crews continued installing supply ductwork for unit 3B. 
  • The contractor continued insulating ductwork and heating hot water lines for unit 3A and 3B. 
  • They removed ceiling tile from Room 3312N. 
  • The contractor continued installing the controls for units L2A and L3A in the Administration Building. 

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued pressure washing the north and south side of the Power Plant.