Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, JULY 18, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: 

  • The contractor started framing the monumental stairwell enclosure. 

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding the diesel fuel line casing on the 1st Floor.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit on the 2nd Floor.
  • The freight elevator shaft wall in the basement was poured.
  • Crews continued installing the 6 inch domestic waterline in the basement.
  • No work today on pile caps due to inclement weather.  9 of 12 pile caps have been formed, rebar has been installed in 7 of 12 pile caps and concrete has been poured for 4 of 12 pile caps.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor made final preparations for the exhaust fan lift.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing heating hot water lines for unit 6A in the Clinic Building. 
  • They continued installing supply ductwork for unit 3A and insulating ductwork and heating hot water lines for units 3A and 3B.