Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, JULY 20, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: 

  • The contractor continued framing the monumental stairwell enclosure and installed sheetrock near the rear wall of the auditorium.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding the diesel fuel line casing on the 1st Floor.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit on the 1st Floor.
  • Metal stud bracing was installed along the corridor wall on the 2nd Floor.
  • Workers continued installing the 6 inch domestic water line in the basement.
  • The contractor continued installing forms in the Lakeside lot.  Formwork completed: 12 of 12; rebar installed: 7 of 12; and concrete poured: 4 of 12.

CSRB EXHAUST UPGRADE PROJECT:

  • The new exhaust fans have been lifted onto the roof.
  • Installation of the exhaust fans is underway.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing ductwork for unit 6A in the Clinic Building. 
  • They continued installing heating hot water lines for units 6A and 3A and insulating chilled and heating water lines for unit 3A. 
  • Crews continued installing control wire for units 3A and 3B. 
  • The contractor started framing the hard ceiling in the Mens restroom on the 3rd Floor. 

DENTAL CAMPUS BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued to remove existing caulk and install new caulk on the east and south side of the Power Plant.