Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, JULY 22, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit on the 1st Floor.
  • Workers continued installing metal stud bracing along the corridor wall on the 2nd Floor.
  • The contractor continued installing 6 inch domestic water piping in the basement.
  • No work in the Lakeside lot today due to weather.  Formwork completed: 12 of 12; rebar installed: 9 of 12; and concrete placed: 4 of 12.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing ductwork for unit 6A in the Clinic Building.
  • They demolished the existing outside air duct for unit 3A. 
  • Crews continued installing heating hot water lines for units 6A and 3A. 
  • The contractor continued insulating chilled and heating water lines for unit 3A. 
  • The controls contractor continued installing control wiring for units 3A and 6A. 
  • The contractor continued framing the hard ceiling in the Mens restroom on the 3rd Floor. 
  • They continued installing drop in ceiling on the 3rd Floor.