Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, JULY 27, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION:

  • The contractor is installing gypsum board in the mechanical room behind the 2nd Floor auditorium.
  • Workers are installing ceiling grid in the hallway on the MEB side of the auditorium.
  • The contractor started installing sprinkler heads in the auditorium and the hallway on the MEB side of the auditorium.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit on the 1st Floor.
  • They started installing the high pressure steam line in the basement.
  • Concrete was poured for pile caps in the Lakeside Lot.  Formwork completed: 12 of 12; rebar installed: 12 of 12; and concrete poured: 9 of 12.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing fresh air and supply air duct for unit 3B in the Clinic Building.   
  • Crews insulated supply duct in the bathroom and the corridor on the 6th Floor (unit 6A). 

DENTAL CAMPUS BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued removing old caulk and installing new caulk on the north, south, and west sides of the Power Plant.