Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, JULY 6, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: 

  • The contractor continued installing the metal framing for the auditorium wall panel system.  
  • The glass railing surrounding the monumental staircase was removed. 
  • Additional AV conduit was run on the 2nd Floor.   

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding the diesel fuel line casing on the 1st Floor.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduits on the 3rd Floor.
  • Seven (7) pile caps have been formed up in the Lakeside lot. Five pile caps remain to be formed.
  • Crews continued installing concrete forms for the freight elevator shaft wall in the basement.
  • The contractor continued installing metal support framing for the corridor wall along the 3rd Floor.

CSRB EXHAUST PROJECT:

  • The contractor continued removing exhaust ductwork on the 2nd Floor.
  • Workers welded the exhaust fan frames for exhaust fan systems 2 and 4 on the roof.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing heating hot water lines and supply ductwork for unit 3A in the Clinic Building. 
  • They continued to insulate ductwork for unit 3A. 
  • The contractor set additional VAV boxes for 6A.
  • The controls contractor wired the control panel for L2A in the Administration Building. 

DENTAL CAMPUS BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued caulking on the west side of the Clinic Building and caulking the columns on the ground level of both Administration & Clinic Buildings.