Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, JULY 7, 2011

ALLIED HEALTH/NURSING BLDG PERMANENT REPAIRS & MITIGATION: 

  • The contractor continued prefabricating chilled water lines.
  • Workers removed light fixtures and the plaster ceiling above the monumental stairs. 
  • Additional conduit for the audio/visual equipment was installed on the 2nd Floor.

RESOURCE CENTER PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding the fuel line casing on the 1st Floor.

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduits on the 3rd Floor.
  • Concrete forms for the pile cap nearest the loading dock in the Lakeside lot were erected.
  • The contractor continued forming the freight elevator shaft wall in the basement.
  • They continued installing metal support framing for the corridor wall along the 3rd Floor.

CSRB EXHAUST UPGRADE:

  • The contractor continued removing exhaust ductwork on the 2nd Floor.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor started installing heating hot water lines for unit 6A in the Clinic Building. 
  • Crews continued installing supply ductwork for unit 3A and insulating ductwork and heating hot water lines for units 3A and 3B. 
  • The contractor installed ceiling and light fixtures for unit 3A above the Radiology clinic area.
  • The installed supply ductwork for unit L3A in the Administration Building.   

DENTAL SCHOOL BLDG EXTERIOR WATERPROOFING PROJECT:

  • The contractor continued caulking on the west side of the Clinic Building and caulking the columns on the ground level of both the Administration and Clinic Buildings.