Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, AUGUST 10, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor installed additional conduit on the 2nd Floor.
  • Workers continued installing bracing along the corridor wall on the 1st Floor and the steam supply line in the basement.
  • The contractor started pouring concrete for the grade beam in the Lakeside Lot. 

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing electrical conduit on the 7th Floor to provide power to rooftop exhaust system #3.
  • Crews are installing the round exhaust ductwork for Phase 2A of the upgrade project.
  • They began removing the ceiling tile in Room 342.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued insulating the heating hot water line for unit 6A in the Clinic Building. 
  • Fire alarm wiring for units 3A, 3B, and 6A is being installed.
  • Workers are installing control panels and thermostats on the 3rd Floor of the Clinic Building. 
  • The doorframe and the CMU block surrounding the door frame that lead to unit 3A were installed. 
  • The contractor started the demolition of ceilings and lights in preparation for replacing AHU 5A in the Clinic Building.