Louisiana State University Health Sciences Center Administration & Finance
 

TUESDAY, AUGUST 23, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit on the 2nd Floor.
  • Excavation for the new building storm drain line has begun.
  • Crews continued to build the concrete forms and install the steel rebar for the grade beam by the auditorium side of the building.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing three (3) VFDs (Variable Frequency Drives) on the roof for exhaust system 9.
  • The ductwork in Room 708 was cut and capped.
  • Workers continued to connect the exterior perimeter rooms on the 2nd Floor to the new exhaust ductwork installed in Phase 2A.

DENTAL SCHOOL AHU REPLACEMENT PROJECT: 

  • The contractor poured the concrete pad for (the new) unit 5A in the Clinic Building.
  • They continue insulating chill water pipe and supply duct for unit 6A
  • Workers continued removing light fixtures and ceiling tiles in the Library.