CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit on the 1st and 2nd Floors.
  • Workers continued installing the storm drain line for the new elevated structure.
  • They continued building the concrete forms and installing steel rebar for the grade beam on the auditorium side of the building.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing the three (3) VFDs on the roof for exhaust system #9.
  • Ductwork for exhaust system #9 is being installed in Room 729.
  • Crews continued insulating the ductwork that was installed as part of phase 2A.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor installed three (3) additional VAV boxes for unit 5A in the Clinic Building.
  • They continued installing heating hot water lines for the VAV boxes and the ductwork for unit 5A.