Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, AUGUST 29, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit on the 1st and 2nd Floors.
  • They continued installing the controller for the front passenger elevators.
  • Crews are building the concrete forms and installing steel rebar for the bollards in the Lakeside lot.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing ductwork for exhaust system #3 in the 7th Floor mechanical room and through the roof.
  • Workers continued to install the ceiling support framing in the 2nd Floor corridors.
  • Vibration isolators are being installed on the exhaust fans for exhaust system #10.
  • The contractor installed wiring on the 7th Floor for exhaust systems #9 and 10.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued connecting heating hot water lines for the VAV boxes associated with unit 5A in the Clinic Building.
  • They continued to install ductwork for unit 5A.
  • Crews are removing the ceiling, ceiling grid and lights as they prepare to remove and replace air handling unit 2A in the Clinic Building.