Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, AUGUST 3, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit on the 1st Floor.
  • They continued installing bracing along the corridor wall on the 1st Floor.
  • Workers continued installing the high pressure steam line in the basement and building forms for the columns in the Lakeside Lot. 

CSRB EXHAUST UPGRADE PROJECT:

  • The air plenum base for exhaust system #10 was installed on the roof.
  • The contractor continued installing electrical conduit on the 7th Floor to provide power to the rooftop exhaust system #2.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing heating hot water lines for unit 6A in the Clinic Building. 
  • Crews continued to install the sheetrock ceiling for the Men’s restrooms on the 3rd and 6th Floors.  
  • They continued installing supply air duct in the 6th Floor mechanical room and both control panels on the 3rd Floor. 
  • The breakers for both units on the 3rd Floor were installed. 
  • The contractor insulated the supply duct for unit L3A in the Administration Building.
  • They started installing duct detectors for units L2A and L3A.