Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, AUGUST 31, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit on the 1st and 2nd Floors.
  • They continued installing the controller for the front passenger elevators.
  • Crews installed the metal deck for the new loading dock in the Lakeside lot.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor installed ductwork for exhaust system #9 in Room 342.
  • Workers continued installing the ceiling support framing in the 2nd Floor corridors.
  • Fire sprinklers are being installed in the 2nd Floor corridor.
  • The contractor continued installing wiring on the 7th Floor for exhaust systems #9 and 10.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued running heating hot water lines to the VAV boxes for unit 5A in the Clinic Building.
  • They continued installing ductwork for unit 5A.
  • The contractor started installing the chilled water lines for unit 5A.
  • Workers removed additional ceiling grid and lights in preparation for the removal of unit 2A in the Clinic Building. 
  • Ceiling grid was installed for unit 6A. 
  • The contractor started installing ductwork in the Library.