Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, AUGUST 5, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit on the 1st Floor and installing bracing along the corridor wall.
  • Crews continued installing the high pressure steam line in the basement and steel rebar for the grade beams in the Lakeside Lot. 

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor installed roof flashing around exhaust systems #9 and #10.
  • They continued installing electrical conduit on the 7th Floor to provide power to the rooftop exhaust system #1.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor started insulating the heating hot water line for unit 6A in the Clinic Building. 
  • Workers began installing the fire alarm wire for unit 6A. 
  • The new ceiling is being installed in the 3rd Floor corridor of the Clinic Building.
  • The contractor continued installing both control panels and thermostats on the 3rd Floor.