Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, SEPTEMBER 12, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit on the main lobby of the 1st Floor.
  • The installation of the elevator car rails for the front passenger elevators is completed.
  • The sump pump for the front passenger elevators pit has been connected.
  • Crews continued installing formwork for the 2nd section of the flood wall around the parking garage.
  • The contractor installed galvanized steel bollards in the Lakeside lot.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing ductwork on the 3rd Floor for Exhaust System #9.
  • They continued plastering the ceiling in the 2nd Floor corridors.
  • The VFDs for exhaust system #4 are being installed.
  • The contractor continued insulating the duct risers for exhaust systems #9 & 10.

DS CLINIC AHU REPLACEMENT   

  • The contractor continued to run the heating hot water lines to the VAV boxes for unit 5A in the Clinic Building.
  • The chilled water lines for unit 5A have been painted.
  • The contractor continued to install the VAVs and insulate the ductwork for unit 2A in the Clinic Building. 
  • Crews are insulating the heating hot water lines in the Library and continue to install the electrical conduit for the new ceiling layout.
  • The contractor continued installing control wire to the VAVs for unit L3A in the Administration Building.