CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit on the main lobby of the 1st Floor.
  • Crews continued installing formwork for the 2nd section of the flood wall around the parking garage.
  • The contractor completed installing galvanized steel bollards in the Lakeside lot.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor pressure tested the duct riser for fan system #4.
  • They continued installing the VFDs for exhaust system #4.
  • Workers continued plastering the ceiling in the 2nd Floor corridors.
  • The contractor continued insulating the duct risers for exhaust systems #9 & 10.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued to run the heating hot water lines to the VAV boxes for unit 5A in the Clinic Building.
  • Crews continued installing VAVs and insulating the ductwork for unit 2A in the Clinic Building. 
  • The new AHU 2A was set in place.
  • The contractor continued insulating the heating hot water lines and installing electrical conduit for the new ceiling layout in the Library.
  • Unit L3A was started up and workers continued installing control wire to the VAVs.