Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, SEPTEMBER 28, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing the steel structure for the 4th level of the new building in the Lakeside lot.
  • Workers continued installing conduits along the 1st Floor corridor.
  • The contractor removed the concrete forms from the flood wall in the parking garage.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing the VFDs for exhaust system #1.
  • They are installing ductwork in Rooms 533A and 412G.
  • The plaster ceiling in the feed room on the 1st Floor was painted.
  • The contractor began repairing the ceiling in the BSL3 Lab.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing supply and fresh air duct on the 2nd Floor of the Clinic Building.
  • They continued to install the ceilings in the 2nd and 5th Floor restrooms and the ceiling grid on the 5th Floor.
  • Workers continued installing CMU blocks surrounding the 2nd Floor mechanical room door frame.
  • The supply and heating hot water lines on the 2nd Floor are being insulated. 
  • The contractor started up unit 5A; the unit is currently running in hand. \\
  • Crews continued moving the Library stacks back into place. 
  • The contractor started demolishing electrical and pneumatic conduit in the 4th Floor (Admin. Bldg.) mechanical room.