CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding the steel structure for the new MEP building.
  • They continued roughing in for exterior light fixtures in the new loading dock area.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor installed ductwork on the 6th and 7th Floors for exhaust systems #1 and #2.
  • Workers continued to install the wall and floor protection in the 2nd Floor corridor.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing the heating hot water lines for unit 5B in the Clinic Building. 
  • Crews started insulating ductwork for unit 5B and installed transitions for unit 5B. 
  • The contractor demolished a CMU block wall to provide access to the mechanical room for the installation of unit 7D. 
  • The asbestos contractor completed removing ductwork from the 7th Floor. 
  • The contractor set units L4C and L4D in place in the Administration Building. 
  • Workers demolished heating hot water lines.
  • The abatement contractor removed ductwork and insulation in the Library workroom.