Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, OCTOBER 19, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued welding the steel structure for the new MEP building.
  • The construction of the CMU wall for the transformer vault has begun.
  • The drain line for the new MEP building is being installed.

CSRB EXHAUST UPGRADE PROJECT:

  • Crews continued to remove the ceilings in the 2nd Floor corridor.
  • Shaft walls are being installed around the exhaust riser for fan system #3.
  • The contractor began running the wiring to fan systems 1 and 2.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing heating hot water lines and supply ductwork for unit 5B in the Clinic Building.
  • Workers installed supply ductwork and installed the drip pan for unit 7A. 
  • Light fixtures and ceilings are being removed from the 6th Floor offices. 
  • The asbestos contractor continued removing ductwork from the 6th Floor.   
  • The contractor is installing chilled water lines to units L4C and L4D in the Administration Building.  
  • They continued removing lights in the Library office area. 
  • Crews started replacing the exterior louvers on the 1st Floor of the Administration Building.