CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued constructing the CMU wall for the transformer vault and roughing in exterior light fixtures for the new building.
  • Workers continued to weld the steel structure for the roof level of the MEP building.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor finished removing the ceilings in the 2nd Floor corridor.
  • They continued installing shaft walls around the exhaust riser for fan system #3 on the 4th Floor.
  • Crews continued installing wiring to fan systems 2 and 4.
  • A cross connection was installed in exhaust riser #1 on the 5th Floor.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing the heating hot water and chilled water lines for unit 5B in the Clinic Building.
  • The installation of the supply ductwork for units 5B and 7A continued.
  • The contractor started the demolition of unit 6A.
  • New ductwork is being installed in the 2nd half of the Library.  
  • The heating water lines in the Library were capped.
  • All of the old ductwork in the 2nd half of the Library has been removed.   

DENTAL SCHOOL ADMIN 1ST FL ABATEMENT:

  • The abatement project that will prepare the Dental Administration Building 1st Floor for the permanent repairs and hazard mitigation has begun.
  • Old ductwork is being removed from the 1st Floor.