CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued constructing the CMU wall for the transformer vault and roughing in for the exterior light fixtures and plumbing risers for the new building.
  • Workers continued welding the steel structure for the roof level of the new building.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor removed the insulation from the ductwork in the 2nd Floor corridor.
  • Crews continued to install shaft walls around the exhaust riser for fan system #3 on the 4th Floor.
  • They continued installing the wiring for fan system 1.

DS CLINIC AHU REPLACEMENT   

  • The contractor continued installing heating hot water and chilled water lines for unit 5B in the Clinic Building.
  • The supply ductwork and VAVs for units 7A and 6B are being installed.
  • The demolition of unit 6A is proceeding.
  • Workers continued to install new ductwork in the 2nd half of the Library.  
  • The contactor continued running heating and chill water for the 4th Floor units in the Administration Building. 

DENTAL SCHOOL ADMIN BLDG 1ST FLOOR ABATEMENT:

  • The contactor removed additional ductwork from the 1st Floor.