Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, OCTOBER 28, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued constructing the CMU wall for the transformer vault.
  • They completed roughing in power for the trash compactor.
  • Crews continued installing 6" heating hot water supply and return piping.
  • The contractor started installing the elevator sump pump discharge lines under the 2nd Floor of the MEP building.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing shaft walls around the exhaust riser for fan system #3 on the 2nd Floor.
  • Workers continued installing conduit for the control system wiring for fan system #9.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor completed running the heating hot water lines for unit 5B in the Clinic Building and pressure tested the lines. 
  • The new ductwork for unit 7A was pressure tested.
  • The contractor continued installing supply ductwork and the VAVs for unit 6B.  
  • The VFD for unit 7A was installed. 
  • The contractor continued installing and insulating ductwork in the Library. 
  • They continued installing VAVs in the Library.  

DENTAL SCHOOL ADMIN BLDG 1ST FLOOR ABATEMENT:

  • The contractor continued removing ductwork and insulation from the 1st Floor.