Louisiana State University Health Sciences Center Administration & Finance
 

MONDAY, OCTOBER 31, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued to construct the CMU wall for the transformer vault.
  • Workers installed conduits on the 2nd Floor corridor leading to the new MEP building.
  • They continued installing the elevator sump pump discharge lines under the 2nd Floor of the MEP building.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing shaft walls around the exhaust riser for fan system #3 on the 2nd Floor.
  • They are installing conduit for the control system for fan system #9.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor started insulating the heating hot water lines for unit 5B in the Clinic Building.   
  • The heating water lines for unit 7A are being installed.
  • The installation of the supply ductwork and VAVs for unit 6B continues.  
  • The contractor continued to install and insulate new ductwork in the Library. 
  • They continued installing VAVs in the Library.  

DENTAL SCHOOL ADMIN BLDG ABATEMENT PROJECT:

  • The contractor continued removing ductwork and insulation from the 1st Floor.