Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, OCTOBER 7, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor is roughing in for the exterior lighting for the new MEP building.
  • They continue to apply waterproof coating for the parking garage flood wall.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing the VFDs on the roof for exhaust system #1.
  • A new motor was installed for fan 3A.
  • The new exhaust riser for exhaust #1 is being insulated.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor demolished the old chilled water lines for unit 7D in the Clinic Building. 
  • Crews continued installing supply ductwork and VAVs for unit 5B.
  • Ceiling grid is being installed in the 2nd Floor clinic area. 
  • The contractor welded the metal pan for unit 5B. 
  • The chill water bypass loop was installed in the L4C/L4D mechanical room in the Administration Building.