Louisiana State University Health Sciences Center Administration & Finance
 

WEDNESDAY, NOVEMBER 16, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit from the back corridor to the MEP building on the 3rd Floor.
  • Workers continued to install the storm drain pipes on the 2nd level of the MEP building.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing conduit for the control wiring for fan system #1.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The VFDs for units 7A and 6B were started up. 
  • The contractor continued insulating ductwork, installing ductwork transitions, and installing chilled and heating hot water lines for unit 6B in the Clinic Building.  
  • Crews continued insulating the chilled and heating hot water lines for units 7A and 7D.
  • They continued demolishing units 6D and 6E. 
  • Workers are removing lights and ceilings for unit 4A in the Clinic Building.
  • The contractor started demolishing units L2B and L3B in the Administration Building and continued removing the associated piping.  
  • They continued installing light fixtures in the Library. 
  • The slate panels in front of the L4C/L4D mechanical room are being installed.