CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued constructing the CMU wall for the transformer vault and installing conduits on the 2nd Floor corridor leading to the MEP building.
  • Crews continued installing metal decking on the 3rd level of the MEP building.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor began installing conduit for the controls of fan system #4.
  • Fan 3C was attached to the support framing.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued insulating heating hot water and chill water lines for unit 5B in the Clinic Building.   
  • The supply ductwork and VAVs for unit 6B are being installed.  
  • Workers continued installing heating hot water lines and transition supply ductwork for unit 7A.
  • Control wiring for the 2nd and 5th Floors of the Clinic Building is being run. 
  • The contractor continued installing and insulating new ductwork in the Library.
  • The heating hot water lines are being installed in the Library.  
  • The CMU block wall of the mechanical room on the 4th Floor of the Administration Building was replaced.

DENTAL SCHOOL ADMIN BLDG 1ST FL ABATEMENT:

  • The contractor continued removing ductwork and insulation from the 1st floor.