CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor installed conduit in back corridor leading to the MEP building.
  • Crews continued installing the 2" steam piping line in the basement.
  • Door frames were set in the corridor leading to the MEP building.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor started installing conduit for the controls of fan system #3.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing ductwork transitions and insulating the ductwork for unit 6B in the Clinic Building.  
  • They started installing the chill and heating hot water lines for unit 6B. 
  • Workers continued installing chill and heating hot water lines for units 7D and 7A.
  • Control wiring for the 2nd, 5th and 7th Floors is being installed. 
  • The contractor started installing ceilings in the Library and for unit L2B. 
  • They continued installing heating hot water lines in the library.
  • Ductwork for unit L4C in the Administration Building is being installed.
  • The contractor insulated chill and heating hot water lines for units L4C and L4D. 

DENTAL SCHOOL Admin bldg 1st floor abatement:

  • The contractor continued removing ductwork and insulation on the 1st Floor.