Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, DECEMBER 2, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit and storm drain pipes on the 3rd level of the MEP building.
  • Crews removed the concrete forms for the steps to the loading dock, the roof of the new transformer vault, and areaways 5, 6, and 7.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor installed the fan motor EF-2B.
  • The control panel enclosure for fan system #10 was installed.

DENTAL SCHOOL AHU REPLACEMENT PROJECT: 

  • The contractor started installing unit 4A in the Clinic Building.  
  • They continued installing heating hot water lines for unit 4A. 
  • The contractor started insulating heating hot water on 6B.
  • Workers continued installing the ceiling in the Men’s restroom and elevator lobby on the 7th Floor.  
  • The contractor continued installing ductwork and VAVs for unit L2B in the Administration Building. 
  • Crews continued installing chilled water lines and control wire for units L2B and L3B. 
  • The contractor continued installing ceiling grid in the Library offices.