CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduit on the 3rd LEVEL of the MEP building.
  • Crews continued installing storm drain pipe on the 2nd level of the MEP building.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing the new exhaust ductwork for phase 2B.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor finished installing the heating hot water lines for unit 2B in the Clinic Building and pressure tested the lines.
  • Workers continued to insulate the new ductwork for unit 2B. 
  • Work continues on the controls for the new air handling units. 
  • The contractor continued removing ceiling grid and lights for units 7B, 7C and 4B.  
  • The contractor continued insulating the chilled and heating hot water lines for units L2B and L3B in the Administration Building.   

DENTAL SCHOOL FOOD COURT:

  • The contractor demolished the plaster wall for the old telecom room in the basement.