TUESDAY, DECEMBER 6, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit and storm drain pipes on the 3rd level of the MEP building.
  • They continued installing electrical conduit on the 2nd level of the MEP building.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor rerouted plumbing in corridor of the 2nd Floor.
  • They removed the temporary power feed for the exhaust fans.
  • The exhaust fan control for fan systems 1, 2, 3, 4, and 10 was installed.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • Workers started removing ceiling grid from the 2nd Floor clinic areas.
  • The contractor continued installing heating hot water and chilled water lines for unit 4A in the Clinic Building.
  • The mechanical room door frame for unit 4A was set. 
  • The contractor continued insulating the heating hot water lines for unit 6B.
  • Crews continued installing the ceiling in the Men’s restroom on the 7th Floor.
  • The contractor continued installing ductwork and VAVs for unit L2B in the Administration Building. 
  • They continued installing chilled water lines and control wire for units L2B and L3B and L4C and L4D. 
  • The contractor continued installing lights in the Library offices.