CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing conduit and storm drain pipes on the 3rd level of the MEP building.
  • They continued installing electrical conduit on the 2nd level of the MEP building.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued rerouting plumbing in corridor of the 2nd Floor.
  • The temporary ductwork was installed in the 2nd Floor corridor.
  • The control wiring for fan system 3 was installed.

DS CLINIC AHU REPLACEMENT  

  • The contractor continued removing ceiling grid in the 2nd Floor clinic areas.
  • Crews continued installing heating hot water and chilled water lines for unit 4A in the Clinic Building.
  • The mechanical room door frame for unit 4A was installed. 
  • Workers continued insulating heating hot water lines for unit 6B.
  • The contractor continued installing ceiling grid on the 6th Floor. 
  • They continued installing the ceiling in the Men’s restroom on the 7th Floor.
  • The contractor started installing the ductwork transitions for unit L2B in the Administration Building. 
  • They started installing the heating water lines for units L2B and L3B. 
  • The contractor continued installing lights in the Library offices.