Louisiana State University Health Sciences Center Administration & Finance
 

THURSDAY, DECEMBER 8, 2011

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor pressure tested steam pipes and chill water pipes in the basement.
  • Crews continued installing electrical conduit on the 2nd level of the MEP building.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor continued installing the temporary ductwork in the 2nd Floor corridor.
  • The control wiring for fan system 1 was installed.

DS CLINIC AHU REPLACEMENT  

  • The contractor continued removing ceiling grid in the 2nd Floor clinic areas in the Clinic Building.
  • They continued installing heating hot water and chilled water lines for unit 4A. 
  • Workers continued insulating the heating hot water lines for unit 6B.
  • The contractor continued installing ceiling grid and started installing light fixtures on the 6th Floor. 
  • They continued installing the ceiling in the Men’s restroom on the 7th Floor.
  • The contractor started installing the ductwork transitions for unit L2B in the Administration Building. 
  • The heating water lines for units L2B and L3B are being installed.