Louisiana State University Health Sciences Center Administration & Finance
 

FRIDAY, JANUARY 13, 2012

CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued fireproofing the structural steel of the MEP building.
  • They continued installing electrical conduit on the 3rd level of the MEP building.

CSRB EXHAUST UPGRADE PROJECT:

  • The contractor sealed the new exhaust ductwork installed as part of phase 2B.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor pressure tested the chilled water lines for unit 2B in the Clinic Building. 
  • Workers continued to insulate the ductwork for units 7B & 7C.
  • The contractor continued installing the heating hot water lines for 7B.
  • The concrete pad for unit 7B was poured.
  • The contractor installed control wires for unit L2B in the Administration Building.

DENTAL SCHOOL ADMIN BLDG FOOD COURT:

  • The contractor continued to install the break metal along the curves in the terrazzo floors. 
  • Crews continued the installation of the HVAC ductwork in the kitchen area.

HUMAN DEVELOPMENT CENTER:

  • The contractor continued to perform the load test for piles.