CEB PERMANENT REPAIRS & MITIGATION:

  • The contractor continued installing electrical conduit on the 3rd level of the MEP building.
  • Crews continued working in the elevator pits 1, 2, and 3.
  • They continued fireproofing the structural steel of the MEP building.

DENTAL SCHOOL AHU REPLACEMENT PROJECT:

  • The contractor continued installing VAVs and ductwork for units 7B and 7C in the Clinic Building.
  • Workers continued insulating the heating hot water lines for unit L2B in the Administration Building.

DENTAL SCHOOL ADMIN BLDG FOOD COURT:

  • The contractor marked floor penetrations for the plumbing.
  • Cracks in the existing terrazzo floor are being repaired.
  • The HVAC duct hangers are being installed.

HUMAN DEVELOPMENT CENTER:

  • The contractor continued driving test piles.