Louisiana State University Health Sciences Center Administration & Finance
 

Wednesday, April 19, 2006

  • There are a few fire alarm system devices that need to be replaced on the 5th and 10th floors of the Nursing/Allied Health Building and the contractor is securing these now. We still anticipate receiving approval from the State Fire Marshal to reoccupy the building as scheduled.
  • The new emergency telephones are being installed in the MEB elevators. When completed, the State Elevator Inspector can complete his inspection and certify them for use.
  • Environmental Remediation:
    • The cleaning of the HVAC system is finished at the Residence Hall. LSUHSC personnel are installing new filters and testing each fan.
    • The contractor is removing glue from the 1st floor slab in the Resource Center where floor tiles were removed.
    • The final cleaning is being done in Stanislaus Hall.
    • The more extensive work of removing drywall, etc. on the 1st floor of the Nursing/Allied Health Building is still in progress.
    • The contractor will be cleaning elevator pits this weekend.
    • The contractor expects work under the contract to be 100 percent complete next week.