Louisiana State University Health Sciences Center Administration & Finance
 

Friday, June 23, 2006

  • Reminder: The environmental remediation contractor will stage their equipment for cleaning on the 2nd floor of 1542 Tulane on Saturday, June 24th. Cleaning will begin on Monday, June 26th. At that time, all access to the entire building will end until the cleaning of the building is complete and the subsequent testing clears the spaces for occupancy.
  • Reminder: As noted before, the replacement of the CSRB riser feeders that serve the Perdido side of the building will be completed this weekend, June 23rd and 24th. This work will entail several complete power outages, each less than one hour in duration. Other than the times of complete power outage, the air conditioning, ventilation and emergency power will be available. Please see the email transmitted this afternoon for the specific times of planned outages. Also, to protect the network equipment in the building it will be turned off, so network connectivity to and from CRSB will not be available between 5:15pm on 6/23/06 and 8:00am on 6/25/06.
  • The pump out of the elevator pits in the Clinic and Administration Buildings at the Dental School is scheduled to be completed over the weekend.
  • The temporary domestic water pump is currently being installed at the Dental School.