Louisiana State University Health Sciences Center Administration & Finance
 

Thursday, June 29, 2006

  • The city pumps, soft water pumps, air dryers for the air compressors, and the expansion tank for hot water have been installed at the Dental School.
  • The new exhaust fan for the Resource Center has been delivered and is on the roof. It will be installed shortly.
  • The temporary power for the P-3 lab at 1542 Tulane Ave. is connected but not yet energized.