Louisiana State University Health Sciences Center Administration & Finance
 

Thursday, April 12, 2007

  Dental School :

  • ADC continued to install the network equipment in Room 5312 of the Clinic Building.
  • Zimmer started the removal of the carpet on 2nd floor of the Administration Bldg.
  • MCC began installing the Chemical Treatment System on the first floor of the Power Plant.
  • The elevator contractor began installing new floor tile in Elevator #3 in the Clinic building. 
    • Also they started running a 2" conduit to each motor for the passenger elevators in the Administration Building .

 1542 Tulane:

  • Ordes Electrical began the process of removing the old starters for #1 and #2 sump pumps and installing the new controllers. 
  • Stratos Elevators had ISE Electrical install smoke alarms in elevators shafts #1, #2 and #3.  
  • Arc Mechanical installed new check valves and finished the repairs to the condensate return station.